As you may have read in A6581's thread, an imminent mega shunt is to occur here at Swithland. And during this progress, it is hoped DB992447 will be moved closer to our work area and work then hopefully commence on its overhaul.
Work required:
Clean and paint the under frame
test vacuum cylinder and possibly overhaul
weld a new plate to hopper where rotten, only on one discharge side so not a big job
clean inside and outside hopper
overhaul the release mechanism
repaint into Indian red
Hopefully this should take 2 years maximum to achieve, with one person working on it once a week. If you would like to help progress this project, or any of our other projects then please do get in touch. Your help will be greatly appreciated. Our contact details can be found on our web site